calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Bridge over Rhine in Basle

Switzerland

The line connecting the 'SBB' and 'Badischer Bahnhof' stations in Basle is being given a second twin track. The principle structure of this upgrade project is a new, second bridge
over the Rhine. This is being built parallel to both the existing railway bridge and to a motorway viaduct, and is being formed using a pair of Doka cantilever forming travellers.

Back

Project data

Year of completion
2012
Project duration
12 Months
Country
Switzerland
Town or city
Basle
Realization
JV 'ARGE Rheinbrücke Basel'
Structure
Bridge
Type of structure
Cantilevering

Cantilevered parapet

Construction method
Straight
Cross-sectional shape
Single-cell box girder – straight webs
Overall length of bridge
237 m
Longest span
112 m
Number of piers
2
Length of concreting section
3.90 m
Number of casting sections
52