calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

YOUI Headquarter Building

Australia

With the construction of the $68 m building, Youi is set to establish their global headquarters on Queensland’s Sunshine Coast. It is understood that the project is the largest non-government related investment in Sunshine Coast’s history and one of the largest in regional Australia. The HQ building will initially house 900 staff and is designed to accommodate growing staff numbers as the company expands its operations. The purpose built global headquarters will not only be home to all corporate positions but will also include a public outdoor plaza, public recreational facilities, a park and café.

Challenge:
The biggest challenge faced by the client was forming the high decks (5.50m and 4.50m soffits) in a safe and cost effective manner. Productivity was the key factor in the final decision.

Solution:
Dokamatic tables with Eurex 20top550 props were ideally suited for the project. The use of the system results in major saving in labour as the tables are supplied fully assembled to site and are safely and efficiently re-located with the Dokart plus shifting appliance.

Back

Project Details

Year of site completion
2017
Country
Australia
City
Sippy Downs, Sunshine Coast
Contractor
TK Formbuild Pty Ltd