calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Tacagua Viaduct

Venezuela

21 hollow piers with changing wall thickness and caps that were also hollow - hammer type with internal window pier without support from below (floating). Both structures with complex geometry

Back

Project data

Year of completion
2015
Project duration
24 Months
Country
Venezuela
Realization
Consortium Buyaca – La Guaira
Structure
Bridge
Type of structure
Bridge piers and pylons