The Challenges:
The Solution with Customer Benefit:
Why was Doka Selected as the formwork supplier?
“I’m in love with this system. Being a first time user I was skeptical and SuperDek’s biggest critic prior to it arriving onsite. Once we started I couldn’t believe the production rates we were getting using a handset system. The most impressive part aside from the large grid, was how quickly we were able to set and strip the perimeter at the slab edge. This is where production time is always lost on every job I’ve been on. Doka has done it once again!”
Roman Ramirez, Super Intendent – CCK Construction Services
Country
US
City
Disney - Orlando, Florida
Contractors
CCK Construction Services
Type of structure
Hotel
Height
40 ft.
Stories
4 Stories
Cycle time
240 SF per man hour
Sq. Ft
80,000 SF
Construction time
90 days