calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Gasthofalm Bridge

Austria

As part of the phased programme of rehabilitation work on Austria's A10 Tauern Autobahn, the two carriageway slabs of the 436 m long Gasthofalm Bridge were completely rebuilt. Two high-capacity Doka composite forming carriages, which were exactly tailored to the project-specific requirements, were in action here.

Back

Project data

Year of completion
2011
Project duration
11 Months
Country
Austria
Address
A10 Tauern Autobahn, structure E37, Gasthofalm
Realization
Steiner Bau GmbH
Structure
Bridge
Type of structure
Composite construction

Bridge deck/superstructure

Type of carriage/traveller or formwork
Overslung composite forming carriage
Length of bridge (superstructure)
436 m
Width of bridge (superstructure)
14 m
Height of bridge (up to top edge of superstructure)
60 m
Cross-sectional shape of structural steelwork
I-section girder
Clear width of structural steelwork
7.50
Clear height of structural steelwork
3.26
Length of concreting section
23.50 m
Number of casting sections
20
Cycle time
7 -day cycle