calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK

Tisza Bridge

Hungary

Hungary's new M43 motorway branches off the M5 north-west of Szeged, heading towards Romania via Szeged and Makó. This constructional design is a blend of composite and extradosed bridge. This means that the carriageway- and base slabs are made of reinforced concrete, and the webs and crosswalls of steel sheets.

Back

Project data

Year of completion
2010
Project duration
13 Months
Country
Hungary
Town or city
Szeged
Realization
Hídépítő
Structure
Bridge
Type of structure
Cantilevering

Bridge deck/superstructure

Cross-sectional shape
Twin-cell box girder – straight webs
Overall length of bridge
372 m
Longest span
180 m
Number of piers
4
Length of concreting section
5 m
Cycle time
11 -day cycle