calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK

Attraversamento Ferroviario do Sado

Portugal

To keep the distances between the longitudinal girders of the composite forming carriage constant in the broadening zone of the bridge structure and thus ensure a constant track-width, the Doka project engineers devised a system in which the roller trestles are not mounted directly on the longitudinal girders of the structural steelwork (as is usually the case), but on a transverse steel girder.

Back

Project data

Year of completion
2010
Project duration
18 Months
Country
Portugal
Town or city
Lisbon
Realization
Teixeira Duarte Sede Lisboa
Structure
Bridge
Type of structure
Composite construction

Bridge deck/superstructure

Shape
Straight
Type of carriage/traveller or formwork
Overslung composite forming carriage
Length of bridge (superstructure)
2735 m
Width of bridge (superstructure)
15.70 m
Height of bridge (up to top edge of superstructure)
20 m
Cross-sectional shape of structural steelwork
I-section girder
Clear width of structural steelwork
7
Clear height of structural steelwork
2.60
Length of concreting section
31.50 m
Number of casting sections
106
Cycle time
7 -day cycle