calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Tunnel Steinhaus

Austria

This 2.4 km long twin-tube motorway tunnel was constructed in a weekly cycle. The project was awarded for the Austrian engineer's prize 2002 because of the innovative solution of the monolithic construction method. The jury had based their decision on the particularly innovative formwork concept as well as the excellent coordination between the design and execution of construction work.

Back

Project data

Year of completion
2003
Project duration
18 Months
Country
Austria
Address
Wels
Structure
Tunnel
Type of structure
Cut-and-cover tunnel

Wall

Construction method
Monolithic
Cross-sectional shape
Rectangular
Clear width
9,50 m
Clear height
5,50 m
Formed length of tunnel
2400 m
Length of concreting section
24 m
Number of casting sections
100
Cycle time
5 -day cycle