calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Government buildings, Putrajaya

Malaysia

In Malaysia, most governmental institutions are in the administrative capital of Putrajaya, to the south of Kuala Lumpur. The cores of the 40-storey office high-rises 4G10 and 4G1 were cast using Doka's multi-functional Automatic climbing formwork Xclimb 60. The cast-in-place concrete floor slabs and a very large number of edge-beams were constructed using adaptable Dokamatic tables.

Back

Project data

Year of completion
2010
Project duration
24 Months
Country
Malaysia
Town or city
Putrajaya
Realization
Sunway Construction
Structure
Office/administration/multipurpose building
Type of structure
High-rises

Shaft / core

Construction method
Core formed/poured in advance
Number of storeys
45
Structure height
160 m
Height of casting sections
3.90 m
Number of casting sections
41
Cycle time
6 -day cycle

Floor-slab

Construction method
Straight
Number of storeys
45
Structure height
160 m
Height of casting sections
3.90 m
Number of casting sections
41